§ 13.20. Excavation Procedures and Installation of Facilities.  


Latest version.
  • (a)

    Contractors are prohibited from removing or destroying any markings used by a member operator to mark the horizontal route of an underground facility. If markings are no longer visible, the contractor shall stop activities in that vicinity and notify the State One-Call Notification System to have the route marked.

    (b)

    No new underground facility shall be installed in such a way that creates a conflict with an existing underground facility unless the contractor submits a permit drawing showing the existence of the conflict. All conflicts of which the contractor is aware of when applying for a permit shall be disclosed on the permit drawing.

(Ord. of 7-22-2002, § 2, Doc. #020722701)