§ 59.607. Extension of Capacity Reservation Certificates.  


Latest version.
  • Extensions. Up to thirty (30) calendar days before the expiration date of a Capacity Reservation Certificate, the applicant may request an extension, not to exceed twelve (12) months. Any extension shall be contingent upon payment of an additional reservation fee. If the Capacity Reservation Certificate was issued less than three years ago, the extension fee is as set forth for a reservation in Section 59.604. If the Capacity Reservation Certificate was issued three or more years ago, the additional one-year reservation fee shall be an administrative fee of 2% of the sewer impact fee, or $2,000, whichever is less; and the possible refund of the sewer impact fee shall be reduced by 10%. The CMO shall determine whether the extension is warranted, based on the following criteria:

    1)

    Size of the project and the amount of capacity requested. A limit may be put on the amount of capacity that may be extended; and

    2)

    Phasing; and

    3)

    Location of the project; and

    4)

    Capacity availability within the service area; and

    5)

    Reasons for requesting the reservation time period extension; and

    6)

    Whether developer exercised good faith in attempting to acquire a building permit.

    The administration fee is nonrefundable and cannot be credited against impact fees at the time of permitting.

(Ord. of 9-16-1991, Doc. #25096; Ord. of 11-16-1992, Doc. #26149; Ord. No. 2017-4, § 1(Exh. A), 2-27-2017, Doc. #1702271206)