§ 7.306. Responsibility of Bidders and Respondents.  


Latest version.
  • A.

    Standards. Factors which may be considered in determining whether the standard of responsibility has been met include without limitation whether a prospective contractor has:

    1.

    Available the appropriate financial, material, equipment, facility and personnel resources and expertise, or the ability to obtain them, necessary to indicate its capability to meet all contractual requirements;

    2.

    A satisfactory record of performance with the City and other entities;

    3.

    A satisfactory record of integrity and fair dealing;

    4.

    The legal qualifications to contract with the City; and

    5.

    Promptly supplied all necessary information in connection with the inquiry concerning responsibility.

    B.

    Written Determination of Non-Responsibility Required. If a bidder or respondent who otherwise would have been awarded a contract is found non-responsible, the Chief Procurement Officer shall issue a written determination of non-responsibility setting forth the basis of the finding.

(Ord. No. 2012-44, §§ 1, 2(Att. A), 11-5-2012, Doc. #1211051201; Ord. No. 2016-47, § 1, 5-23-2016, Doc. #1605231202)